Finally, en-suite bedroom has been completed. Originally it was the largest room in this flat. Using methods of partitioning we have divided one it in to three rooms.
Demolition works was our target 1 job. Old ceiling and old plaster was stripped out completely.
Existing ceiling was insulated between old wooden joists with 100mm Rockwool Slab Insulation and boarded it with 12.5mm Siniat GTEC Fire Board, also to maintain best fireprotection we have sealed the perimeter with fire foam and completed fire taping to plasterboards.
For better partition strength we have used only 72mm deep tracks on top and bottom, also mastic bead was applied to tracks and abutment studs.
We had a specific abutment detail when we were fixing abutment stud to external wall – uninsulated wall detail. Where we have fixed two strips of boards to 70mm C Stud, DPM and mastic bead. This detail will stop any damp or cold coming from the external wall bricks inside of partition.
Brick walls had a Gypliner wall lining installed. Where internal linings had no insulation, but external wall lining had 50mm Rockwool Slab Insulation and Novia Vapour Barrier (VCL) installed.
Party walls and external lining had 2 skins of boards, both skins used were 15mm Siniat GTEC dB Plasterboard with Acoustic Insulation performance. Internal lining had just single layer of 15mm Siniat GTEC dB Plasterboard with Acoustic Insulation performance.
To maximise height in the room we have made suspended ceiling as tight as possible to existing ceiling. We have used MF type ceiling on this project, metal was supplied by Hadley brand. Also we have built light boxes for spotlights to prevent overheating. MF Ceiling was insulated with single layer of 100mm Rockwool Slab Insulation. 15mm Siniat GTEC dB Plasterboard with Acoustic Insulation performance was used to board ceiling.
Plastering was done in full. We have used Thistle Board Finish on this project. Afterwards we have mist coated en-suite bedroom and complete plaster snagging with task light for better quality.
Finally, we have been able to complete Final Decorations to walls and ceiling. We have painted ceiling in White Matt, by DULUX brand and walls in Dimity 2008 by Farrow and Ball.
Plumbing, coving and joinery were done by other contractor. Electrical works were carried out by our sub-contractor. We have completed 1st fix, 2nd fix and many other connections of various electrical elements. Electrical safety certificate was issued upon handover to client.